Sprint Planning Notes
Last edited by Sarah Chen · Mar 3, 2026
Sprint goal: Complete the document viewer and task list screens. Push notification infrastructure deferred to Sprint 15.
Capacity
- Sarah: 3 days (PM duties split with Brand Redesign)
- Marcus: 5 days (full allocation)
- Priya: 4 days (1 day on API migration)
- James: 5 days (full allocation)
Marcus
Commitments
- MOB-34: Document viewer — rich content rendering (Priya, 3pts)
- MOB-35: Task list — filter and sort (Marcus, 5pts)
- MOB-36: Navigation — bottom tab bar (James, 2pts)
- MOB-37: Offline cache — SQLite setup (Marcus, 3pts)